Based on data from the investment body, Lamda Development, at this stage, 70% of the total volume has already been excavated – with 365,000 cubic meters of soil. Over 7,600 meters of wall and 20,500 cubic meters of base slab concreting have been completed.
The tunnel roof construction work, which started in May 2022, is in progress.
See the video:
The 1.3-kilometre-long underground route will extend from Alimos Beach to the Marina of Agios Kosmas, and according to Lamda Development, the project will make a decisive contribution to decongesting traffic on the coastal front with three lanes in each direction and the removal of 6 traffic lights signals.
READ MORE: The houses in Ellinikon are sold out! The Little Athens project is also moving forward.
This Greek Defense Minister Nikos Dendias, during a visit to Chicago, participated in a wide-ranging…
The United States has frozen foreign aid to most countries, including Ukraine, but exempted Israel…
Three Greek Australians have been recognized for their outstanding contributions to the community in the…
Tennis Australia has reiterated its stance against players competing in Russia after Thanasi Kokkinakis participated…
President Erdoğan's declaration that Eskişehir's "borders" extend to Thessaloniki, Cyprus, Crimea, and Samarkand has reignited…
Greek authorities have broken up a drug ring in Athens that exploited migrants' healthcare IDs…